The three phases involved in the management of large projects are: |
planning, scheduling and controlling. |
Which of the following does NOT belong to the planning phase of projection management? |
Monitoring resources |
The project organization may be less helpful when: |
the job is familiar to the existing organization |
Which of the following is the THIRD level in work breakdown structure (WBS) |
Subtasks in major tasks |
Gantt charts are |
planning charts used to schedule resources and allocate time. |
Which of the following is NOT part of project controlling? |
sequencing and allotting time to all project activities. |
The critical path of a network is the: |
longest time path through the network |
How is the EF computed? |
ES + Activity time |
Which of these time estimates is NOT used in PERT? |
Standard time |
What is the shortest duration required to complete an activity? |
crash time |
Which of the following is a limitation of PERT and CPM |
There is the inherent danger of placing too much emphasis on the critical path |
Among the following, critical path and slack time analysis MOST help |
pinpoint activities that need to be closely watched |
What is the most popular example of specialized software for managing projects? |
microsoft project |
Which of the following is not a technique that allows managers to plan, schedule, and control, projects? |
factor – rating method |
Which of the following activities are NOT part of project scheduling? |
Make sure all necessary activities are finished in the proper sequence and on time. |
Which of the following is an advanatage of PERT and CPM? |
Straightforward concept and not mathematically complex |
The most realistic estimate of the time required to complete an activity as referred to as? |
most likely tim |
Computerized PERT/CPM reports and charts do NOT include |
probability estimate for on time completion |
Which column in microsoft project defines the precidence relationships among the activites? |
predecessors |
Which of the following is a direct responsibility of the project manager? |
making sure that the people assigned to the project receieve the motivation, direction, and information needed to do their job. |
Which of the following is not used for computation in CPM? |
normal time |
The latest finish of an activity is: |
min (LS of all immediate following activities) |
Which of the following is not true about gantt charts? |
cant charts adequately illustrate the interrelationships between the activites and resources |