Information to develop a project network is collected from the |
Work breakdown structure |
Which of the following represents an activity on an AON project network? |
A node |
Arrows on an AON project network represent: |
Both B and C are correct |
When translated into a project network, a work package will become |
One or more activities |
Which of the following is provided by a project network but not by the work breakdown structure? |
A, B, and C are all correct |
On a project network, the activity times are derived from the |
Work packages |
Part of a project is to Develop Product Specifications. This is best classified as a(n) |
Activity |
An activity that has more than one dependency arrow flowing into it is termed a(n) |
Merge activity |
The critical path in a project network is the |
Longest path through the network |
A/an _________ activity has more than one dependency arrow flowing from it. |
Burst |
An item on a project network is Design Software Completed. This is best described as a(n) |
Event |
Activities which can take place at the same time are termed |
Parallel activity |
A sequence of connected, dependent activities is termed a(n) |
Path |
An AON project network uses which of the following basic building blocks? |
Both A and C are correct |
Which of the following is not one of the basic rules to follow when developing project networks? |
Conditional statements are allowed but looping statements are not allowed |
________ activities must be completed immediately before a particular activity. |
Predecessor |
________ activities are to be completed immediately following a particular activity. |
Successor |
The forward pass in project network calculations determines the |
A, B, and C are all correct |
The backward pass in project network calculations determines the |
Both A and C are correct |
Which of the following correctly calculates the early finish for an activity? |
ES + DUR |
Which of the following correctly calculates the late start for an activity? |
LF – DUR |
The amount of time an activity can be delayed and yet not delay the project is termed |
Total slack |
Which of the following will correctly calculate the total slack in an activity? |
Both A and B are correct |
The laying pipe example in the text illustrates the concept of |
Laddering |
Using a special color copy machine for a tradeshow publication illustrates the concept of |
Hammock activities |
If, for some reason, the project must be expedited to meet an earlier date, which of the following actions would the project manager take first? |
Check to see which activities are on the critical path |
Typically an activity on a project network represents |
One or more tasks from a work package |
Project network logic errors include which of the following? |
Both B and C are network logic errors |
Which company utilized concurrent engineering to design a new line of cars and in the process completed its development six months ahead of schedule? |
Chrysler |
The minimum amount of time a dependent activity must be delayed to begin or end is referred to as: |
Lag |
The requirement for a freshly poured foundation to cure before beginning construction is an example of which of the following type of lag? |
Finish to Start |
Concurrent engineering is a good example of good use of |
Start to Start lags |
If testing cannot be completed any earlier than four days after the prototype is built, which of the following type of lag exists? |
Finish to Finish |
Which of the following represents an activity on an AOA project network? |
A line |
Nodes on an AOA project network represent: |
An event |
Activity |
Task(s) of the project that consumes time while people/equipment either work or wait. |
Activity-on-arrow |
Activity-on-arrow method for drawing project networks. The activity is shown as an arrow. |
Activity-on-node |
Activity-on-node method for drawing project networks. The activity is on the node (rectangle). |
Burst activity |
An activity that has more than one activity immediately following it. |
Concurrent |
Crossfunctional teamwork in new-product development projects that provides product design, quality engineering, and manufacturing process engineering all at the same time. |
Critical path |
The longest activity path(s) through the network. The critical path can be distinguished by identifying the collection of activities that all have the same minimum slack. |
Gantt chart |
A graphic presentation of project activities depicted as a time-scaled bar line. |
Hammock activity |
A special-purpose, aggregate activity that identifies the use of fixed resources or costs over a segment of the project—e.g., a consultant. Derives its duration from the time span between other activities. |
Lag relationship |
The relationship between the start and/ or finish of a project activity and the start and/or finish of another activity. The most common lag relationships are (1) finish-to-start, (2) finish-to-finish, (3) start-tostart, and (4) start-to-finish. |
Merge activity |
An activity that has more than one activity immediately preceding it. |
Parallel activity |
One or more activities that can be carried on concurrently or simultaneously. |
Sensitivity |
The likelihood that the critical path(s) will change once the project begins to be implemented. |
Chapter 6- EBTM 443
Share This
Unfinished tasks keep piling up?
Let us complete them for you. Quickly and professionally.
Check Price