What is the shortest duration required to complete an activity? |
Crash time |
Which is NOT true about project scheduling? |
Project scheduling helps make better use of resources by identifying the non-critical paths through the network |
Gantt charts are.. |
Planning charts used to schedule resources and allocate time |
What is the most popular example of specialized software for managing project? |
Microsoft Project |
What is NOT part of project controlling? |
Sequencing and allotting time to all project activities |
The 3 phases involved in the management of large projects? |
Planning, scheduling, and controlling |
What is a limitation of PERT and CPM? |
There is the inherent danger of placing too much emphasis on the critical path |
The project organization may be less helpful when… |
The job is familiar to the existing organization |
Which of these time estimates is NOT used in PERT? |
Standard time |
How is the EF computed? |
ES+ Activity time |
The latest finish of an activity is? |
Min(LS of all immediate following activities) |
Which column in Microsoft project defines the precedence relationships among the activities? |
Predecessors |
Which of the following is used for computations in CPM? |
Normal time |
Computerized Pert/CPM reports and charts do NOT include… |
Probability estimates for on-time completion |
The most realistic estimate of the time required to complete an activity is referred to as what? |
Most likely time |
Which of the following is NOT true about Gantt Charts? |
Gantt charts adequately illustrate the interrelationships between the activities and the resources |
Which of the following is a direct responsibility of the project manager? |
Making sure that the people assigned to the project receive the motivation, direction, and information needed to do their jobs |
Which of the following activities are NOT part of project scheduling? |
Make sure all necessary activities are finished in proper sequence and on time |
Which of the following is NOT a technique that allows managers to plan, schedule, and control projects? |
Factor-rating method |
Which of the following is an advantage of PERT and CPM? |
Straight forward concept and not mathematically complex |