ch6

Information to develop a project network is collected from the

A. Organization breakdown structure.

B. Work breakdown structure.

C. Budget.

D. Project proposal.

E. Responsibility matrix.

b

Which of the following represents an activity on an activity-on-node (AON) project network?

A. An arrow

B. A line

C. A node

D. Both an arrow and a line

E. An arrow, a line and a node all represent activities

c

Arrows on an activity-on-node (AON) project network represent

A. An activity.

B. Project flow.

C. Dependency.

D. Project flow and dependency.

E. An activity and dependency.

d

When translated into a project network, a work package will become

A. A single activity.

B. One or more activities.

C. A milestone.

D. A critical path.

E. An arrow.

b

Which of the following is provided by both the project network and the work breakdown structure?

A. Dependencies

B. Sequencing

C. Interrelationships

D. Activity duration

E. Timing

d

On a project network, the activity times are derived from the

A. Organization breakdown structure.

B. Work packages.

C. Budget.

D. Project proposal.

E. Responsibility matrix.

b

Which of the following does NOT help describe a project network?

A. A graphic display of the flow and sequence of work through the project

B. Provides the basis for scheduling labor and equipment

C. Gives the times when activities can start and finish and when they can be delayed

D. Highlights major deliverables and identifies their completion dates

E. Identifies critical activities

d

An activity that has more than one dependency arrow flowing into it is termed a(n)

A. Parallel activity.

B. Critical path.

C. Burst activity.

D. Merge activity.

E. Independent activity.

d

The critical path in a project network is the

A. Shortest path through the network.

B. Longest path through the network.

C. Network path with the most difficult activities.

D. Network path using the most resources.

E. Network path with the most merge activities.

b

A(n) _________ activity has more than one dependency arrow flowing from it.

A. Parallel

B. Critical path

C. Burst

D. Merge

E. Independent

c

Which of the following can be used without coordinating with managers of succeeding activities?

A. Total slack

B. Free slack

C. Critical float

D. Float pad

E. Slip pad

b

Activities which can take place at the same time are termed

A. Parallel activity.

B. Critical path.

C. Burst activity.

D. Merge activity.

E. Independent activity.

a

A sequence of connected, dependent activities is termed a(n)

A. Path of events.

B. Parallel path.

C. Activity chain.

D. Path.

E. Dependent chain.

d

Bill is building a project network that involves testing a prototype. He must design the prototype (activity 1), build the prototype (activity 2), and test the prototype (activity 3). Activity 1 is the predecessor for activity 2 and activity 2 is the predecessor for activity 3. If the prototype fails testing, Bill must redesign the prototype; therefore, activity 3 is a predecessor for activity 1. This is an example of

A. Conditional statements.

B. Looping.

C. Having more than one start node.

D. Good network development.

E. Natural network flow.

b

Which of the following is NOT one of the basic rules to follow when developing project networks?

A. An activity cannot begin until all preceding activities have been completed

B. Each activity must have a unique identification number

C. Conditional statements are allowed but looping statements are not allowed

D. An activity identification number must be larger than that of any preceding activities

E. Networks flow from left to right

c

________ activities must be completed immediately before a particular activity.

A. Merge

B. Burst

C. Predecessor

D. Successor

E. Parallel

c

________ activities are to be completed immediately following a particular activity.

A. Merge

B. Burst

C. Predecessor

D. Successor

E. Parallel

d

The forward pass in project network calculations determines all of the following EXCEPT

A. Earliest time an activity can begin.

B. Earliest time an activity can finish.

C. Duration of the project.

D. The critical path.

E. How soon the project can finish.

d

The backward pass in project network calculations determines all of the following EXCEPT

A. Latest time an activity can begin.

B. Earliest time an activity can finish.

C. The critical path.

D. How long an activity can be delayed.

E. Latest time an activity can finish.

b

Which of the following correctly calculates the early finish for an activity?

A. LS + DUR

B. ES + DUR

C. LF + DUR

D. ES + SL

E. LF + SL

b

Which of the following correctly calculates the late start for an activity?

A. EF - DUR

B. ES - DUR

C. LF - DUR

D. ES - SL

E. LF - SL

c

The amount of time an activity can be delayed and yet not delay the project is termed

A. Total slack.

B. Free slack.

C. Critical float.

D. Float pad.

E. Slip pad.

a

Which of the following will correctly calculate the total slack in an activity?

A. LS - ES

B. LF - EF

C. LS - LF

D. LF - ES

E. Either LS - ES or LF - EF

e

The likelihood the original critical path(s) will change once the project is initiated is referred to as

A. Flexibility.

B. Resilience.

C. Sensitivity.

D. Concurrent engineering.

E. Rigidity.

c

Which of the following is true about hammock activities?

A. They are used to identify the use of fixed resources or costs over a segment of a project

B. They are a combination of Start to Start and Start to Finish lags

C. They are activities in which the costs are not subject to change

D. They are an alternative description for the critical path

E. They are highly sensitive

a

If, for some reason, the project must be expedited to meet an earlier date, which of the following actions would the project manager take first?

A. Check to see which activities cost the least

B. Check to see which activities have the longest duration

C. Check to see which activities are on the critical path

D. Check to see which activities have the most slack

E. Check to see which activities have the highest risk

c

The assumption that all immediate preceding activities must be 100% complete is too restrictive in some situations. When an activity is broken down into smaller segments in order to start the succeeding activity sooner, this is called

A. Hammock activities.

B. Concurrent engineering.

C. A forward pass.

D. Dissecting.

E. Laddering.

e

If a project has more than one activity that can begin when the project is to start, a common start node should be used to indicate a clear project beginning on the network. Without a common start node, each path is a

A. Critical path.

B. Parallel path.

C. Dangler path.

D. Multiple start path.

E. Confused path.

c

Tom is responsible for ordering hardware for a custom home his company is building. The contractor installing the hardware is scheduled to start in 5 working days, but the hardware is on backorder and will not arrive for another 9 working days. Fortunately, Tom has 10 days of slack; however, he shares this slack with the hardware installer. He will have to let the contactor know that the hardware will be ready 4 days later than expected and that the slack for the installer has been reduced by 4 days. Tom and the installer share 10 days of

A. Free Slack.

B. Shared Slack.

C. Total Slack.

D. Critical Slack.

E. Functional Slack.

c

The minimum amount of time a dependent activity must be delayed to begin or end is referred to as

A. Hammock.

B. Laddering.

C. Lag.

D. Cushion.

E. Buffer.

c

The requirement for a freshly poured foundation to cure before beginning construction is an example of which of the following type of lag?

A. Start to Start

B. Start to Finish

C. Finish to Finish

D. Finish to Start

E. Any of these could be correct

d

Concurrent engineering, which has dramatically reduced the development time for new products, relies on what kind of lag?

A. Start to Start lags

B. Start to Finish lags

C. Finish to Finish lags

D. Finish to Start lags

E. Any of these could be correct

a

If testing cannot be completed any earlier than four days after the prototype has been built, what type of lag exists?

A. Start to Start

B. Start to Finish

C. Finish to Finish

D. Finish to Start

E. Any of these could be correct

c

When completing a backward pass, you carry the LS to the next preceding activity to establish the LF, unless the next preceding activity is a burst activity, in which case you select

A. The smallest LS of all its immediate successor activities to establish the LF.

B. The largest ES of all its immediate successor activities to establish the LF.

C. The average LS of all its immediate successor activities to establish the LF.

D. The smallest ES of all its immediate successor activities to establish the LF.

E. The largest LS of all its immediate successor activities to establish the LF.

a

System documentation cannot end until three days after testing has started. This is an example of which kind of lag?

A. Start to Start

B. Start to Finish

C. Finish to Finish

D. Finish to Start

E. Any of these could be correct

b

ch6 - Subjecto.com

ch6

Your page rank:

Total word count: 1557
Pages: 6

Calculate the Price

- -
275 words
Looking for Expert Opinion?
Let us have a look at your work and suggest how to improve it!
Get a Consultant

Information to develop a project network is collected from the

A. Organization breakdown structure.

B. Work breakdown structure.

C. Budget.

D. Project proposal.

E. Responsibility matrix.

b

Which of the following represents an activity on an activity-on-node (AON) project network?

A. An arrow

B. A line

C. A node

D. Both an arrow and a line

E. An arrow, a line and a node all represent activities

c

Arrows on an activity-on-node (AON) project network represent

A. An activity.

B. Project flow.

C. Dependency.

D. Project flow and dependency.

E. An activity and dependency.

d

When translated into a project network, a work package will become

A. A single activity.

B. One or more activities.

C. A milestone.

D. A critical path.

E. An arrow.

b

Which of the following is provided by both the project network and the work breakdown structure?

A. Dependencies

B. Sequencing

C. Interrelationships

D. Activity duration

E. Timing

d

On a project network, the activity times are derived from the

A. Organization breakdown structure.

B. Work packages.

C. Budget.

D. Project proposal.

E. Responsibility matrix.

b

Which of the following does NOT help describe a project network?

A. A graphic display of the flow and sequence of work through the project

B. Provides the basis for scheduling labor and equipment

C. Gives the times when activities can start and finish and when they can be delayed

D. Highlights major deliverables and identifies their completion dates

E. Identifies critical activities

d

An activity that has more than one dependency arrow flowing into it is termed a(n)

A. Parallel activity.

B. Critical path.

C. Burst activity.

D. Merge activity.

E. Independent activity.

d

The critical path in a project network is the

A. Shortest path through the network.

B. Longest path through the network.

C. Network path with the most difficult activities.

D. Network path using the most resources.

E. Network path with the most merge activities.

b

A(n) _________ activity has more than one dependency arrow flowing from it.

A. Parallel

B. Critical path

C. Burst

D. Merge

E. Independent

c

Which of the following can be used without coordinating with managers of succeeding activities?

A. Total slack

B. Free slack

C. Critical float

D. Float pad

E. Slip pad

b

Activities which can take place at the same time are termed

A. Parallel activity.

B. Critical path.

C. Burst activity.

D. Merge activity.

E. Independent activity.

a

A sequence of connected, dependent activities is termed a(n)

A. Path of events.

B. Parallel path.

C. Activity chain.

D. Path.

E. Dependent chain.

d

Bill is building a project network that involves testing a prototype. He must design the prototype (activity 1), build the prototype (activity 2), and test the prototype (activity 3). Activity 1 is the predecessor for activity 2 and activity 2 is the predecessor for activity 3. If the prototype fails testing, Bill must redesign the prototype; therefore, activity 3 is a predecessor for activity 1. This is an example of

A. Conditional statements.

B. Looping.

C. Having more than one start node.

D. Good network development.

E. Natural network flow.

b

Which of the following is NOT one of the basic rules to follow when developing project networks?

A. An activity cannot begin until all preceding activities have been completed

B. Each activity must have a unique identification number

C. Conditional statements are allowed but looping statements are not allowed

D. An activity identification number must be larger than that of any preceding activities

E. Networks flow from left to right

c

________ activities must be completed immediately before a particular activity.

A. Merge

B. Burst

C. Predecessor

D. Successor

E. Parallel

c

________ activities are to be completed immediately following a particular activity.

A. Merge

B. Burst

C. Predecessor

D. Successor

E. Parallel

d

The forward pass in project network calculations determines all of the following EXCEPT

A. Earliest time an activity can begin.

B. Earliest time an activity can finish.

C. Duration of the project.

D. The critical path.

E. How soon the project can finish.

d

The backward pass in project network calculations determines all of the following EXCEPT

A. Latest time an activity can begin.

B. Earliest time an activity can finish.

C. The critical path.

D. How long an activity can be delayed.

E. Latest time an activity can finish.

b

Which of the following correctly calculates the early finish for an activity?

A. LS + DUR

B. ES + DUR

C. LF + DUR

D. ES + SL

E. LF + SL

b

Which of the following correctly calculates the late start for an activity?

A. EF – DUR

B. ES – DUR

C. LF – DUR

D. ES – SL

E. LF – SL

c

The amount of time an activity can be delayed and yet not delay the project is termed

A. Total slack.

B. Free slack.

C. Critical float.

D. Float pad.

E. Slip pad.

a

Which of the following will correctly calculate the total slack in an activity?

A. LS – ES

B. LF – EF

C. LS – LF

D. LF – ES

E. Either LS – ES or LF – EF

e

The likelihood the original critical path(s) will change once the project is initiated is referred to as

A. Flexibility.

B. Resilience.

C. Sensitivity.

D. Concurrent engineering.

E. Rigidity.

c

Which of the following is true about hammock activities?

A. They are used to identify the use of fixed resources or costs over a segment of a project

B. They are a combination of Start to Start and Start to Finish lags

C. They are activities in which the costs are not subject to change

D. They are an alternative description for the critical path

E. They are highly sensitive

a

If, for some reason, the project must be expedited to meet an earlier date, which of the following actions would the project manager take first?

A. Check to see which activities cost the least

B. Check to see which activities have the longest duration

C. Check to see which activities are on the critical path

D. Check to see which activities have the most slack

E. Check to see which activities have the highest risk

c

The assumption that all immediate preceding activities must be 100% complete is too restrictive in some situations. When an activity is broken down into smaller segments in order to start the succeeding activity sooner, this is called

A. Hammock activities.

B. Concurrent engineering.

C. A forward pass.

D. Dissecting.

E. Laddering.

e

If a project has more than one activity that can begin when the project is to start, a common start node should be used to indicate a clear project beginning on the network. Without a common start node, each path is a

A. Critical path.

B. Parallel path.

C. Dangler path.

D. Multiple start path.

E. Confused path.

c

Tom is responsible for ordering hardware for a custom home his company is building. The contractor installing the hardware is scheduled to start in 5 working days, but the hardware is on backorder and will not arrive for another 9 working days. Fortunately, Tom has 10 days of slack; however, he shares this slack with the hardware installer. He will have to let the contactor know that the hardware will be ready 4 days later than expected and that the slack for the installer has been reduced by 4 days. Tom and the installer share 10 days of

A. Free Slack.

B. Shared Slack.

C. Total Slack.

D. Critical Slack.

E. Functional Slack.

c

The minimum amount of time a dependent activity must be delayed to begin or end is referred to as

A. Hammock.

B. Laddering.

C. Lag.

D. Cushion.

E. Buffer.

c

The requirement for a freshly poured foundation to cure before beginning construction is an example of which of the following type of lag?

A. Start to Start

B. Start to Finish

C. Finish to Finish

D. Finish to Start

E. Any of these could be correct

d

Concurrent engineering, which has dramatically reduced the development time for new products, relies on what kind of lag?

A. Start to Start lags

B. Start to Finish lags

C. Finish to Finish lags

D. Finish to Start lags

E. Any of these could be correct

a

If testing cannot be completed any earlier than four days after the prototype has been built, what type of lag exists?

A. Start to Start

B. Start to Finish

C. Finish to Finish

D. Finish to Start

E. Any of these could be correct

c

When completing a backward pass, you carry the LS to the next preceding activity to establish the LF, unless the next preceding activity is a burst activity, in which case you select

A. The smallest LS of all its immediate successor activities to establish the LF.

B. The largest ES of all its immediate successor activities to establish the LF.

C. The average LS of all its immediate successor activities to establish the LF.

D. The smallest ES of all its immediate successor activities to establish the LF.

E. The largest LS of all its immediate successor activities to establish the LF.

a

System documentation cannot end until three days after testing has started. This is an example of which kind of lag?

A. Start to Start

B. Start to Finish

C. Finish to Finish

D. Finish to Start

E. Any of these could be correct

b

Share This
Flashcard

More flashcards like this

NCLEX 10000 Integumentary Disorders

When assessing a client with partial-thickness burns over 60% of the body, which finding should the nurse report immediately? a) ...

Read more

NCLEX 300-NEURO

A client with amyotrophic lateral sclerosis (ALS) tells the nurse, "Sometimes I feel so frustrated. I can’t do anything without ...

Read more

NASM Flashcards

Which of the following is the process of getting oxygen from the environment to the tissues of the body? Diffusion ...

Read more

Unfinished tasks keep piling up?

Let us complete them for you. Quickly and professionally.

Check Price

Successful message
sending