Which of the following begins with the due date and schedules the final operation first? |
backward scheduling |
Cycling scheduling is usually used for scheduling |
employees |
Which of the following is NOT a process-focused facility? |
motorcycle assembly line |
Which of the following is NOT an alternative name for finite capacity scheduling? |
finite planning |
Which of the following priority rules minimizes the average number of jobs in the system? |
SPT |
Scheduling matches resources to what? |
customer demands |
What allows operations personnel to manage facility work flows? |
input output control |
Which of the following is NOT one of the criteria used to evaluate scheduling performance? |
maximize WIP |
The sequence of work for a job is also known as its |
routing |
Which of the following breaks down the aggregate plan and develops weekly schedules for specific products or product lines? |
master schedule |
Loading |
is the process of assigning jobs to work or processing centers. |
Which of the following statements is NOT true about process-focused facilities? |
Process-focused facilities are common in high-variety, high-volume manufacturing. |
What are two alternative names for process-focused facilities? |
intermittent and job shop facilities |
What is a technique used to monitor jobs in progress? |
Gantt schedule chart |
Which of the following priority rules minimizes maximum tardiness? |
EDD |
Which of the following statements is NOT true regarding finite capacity scheduling? |
Finite capacity scheduling directs delivery requirements to be based on a set of predefined rules. |
What focuses on developing varying schedules with the minimum number of workers? |
cyclical scheduling |
Which of the following rules does a hospital’s emergency room usually use for treating patients? |
FCFS within a priority class |
Ch. 15 Short Term Scheduling